Charles Sturt University – Energy Performance Contract (EPC Stage 2)

people provide 24/7 engineering support

0

saving pa by upskilling employees to self-deliver specific tasks

£ 0 k

anticipated saving to client by increasing self-delivery of reactive work

0 %

m² covered in terminals 1-5 and the train station

0

// Challenge

highlights

// Solutions

Overview

Following the success of EPC Stage 1, CSU partnered with Conservia once again for the second phase of energy upgrades at Truskett Library in the Bathurst Campus. EPC Stage 2 targeted central plant infrastructure and mechanical system enhancements.

// Challenge

Solution

Conservia focused on replacing aged, inefficient systems with high-efficiency, low-emissions alternatives while continuing the rollout of intelligent control and lighting systems.

// Solutions

Key Measures:

// Challenge

Results

Energy and Gas Savings:

ResourceProposed
Savings
Achieved
Savings
% Over Target
Electricity111,570 kWh/year183,300 kWh/year64%
Natural Gas461 GJ/year480 GJ/year4%

Financial Outcome:

MetricValue
Project Cost~$132,860
Guaranteed Cost Savings~$18,480/year
Achieved Cost Savings~$26,554/year
Savings Over Guarantee$8,074 (43%)
Simple Payback Period7.2 years

Environmental Outcome:

MetricProposedAchieved% Over Target
GHG Savings148 tonnes
CO2-e/year
211 tonnes
CO2-e/year
43% over

More projects

Rising energy costs and increased regulatory pressures regarding environmental compliance posed challenges for ICC Group’s facilities.