Case study · Hospitality
Ageing hotel infrastructure renewed with 100% upfront capital funded through EaaS
100%
Upfront capital funded through EaaS
$650k
Projected annual operating savings
31%
Projected electricity reduction
40%
Projected gas reduction
The building
A 600-room hotel in Sydney’s CBD, operating 24 hours a day, seven days a week.
Originally constructed in the late 1980s, much of the hotel’s mechanical infrastructure was approaching or had exceeded its expected service life. The building required significant investment to maintain reliability, improve energy performance and continue delivering the level of comfort expected by guests.
The challenge
The hotel’s ageing central plant and mechanical systems were becoming increasingly difficult to maintain, with equipment failures creating operational risks.
With only one chiller operational, the hotel had limited cooling capacity and redundancy. A major infrastructure upgrade was needed, but the owner wanted to avoid committing significant upfront capital.
Any solution also needed to minimise disruption to hotel operations, maintain guest comfort and deliver measurable improvements in energy efficiency.
What we changed
Conservia developed a comprehensive infrastructure renewal programme, combining essential asset replacement with energy efficiency improvements.
The project includes:
- Central plant renewal: Replacement of ageing chillers, boilers and associated equipment to improve reliability and energy efficiency.
- Air handling upgrades: Replacement and modernisation of selected air handling units, fans and controls to reduce energy consumption.
- Building Management System: Installation of a new BMS with improved control strategies across heating, cooling and ventilation.
- Domestic hot water: Replacement of ageing equipment with a more efficient hot water system.
- Energy management: Installation of an Energy Management System to monitor performance and identify further optimisation opportunities.
- Lighting and guestroom controls: Targeted upgrades to reduce unnecessary energy consumption.
The project is being delivered within an operating hotel, with works carefully coordinated to minimise disruption to guests and staff.
A different approach to funding
Rather than requiring the owner to fund the infrastructure replacement upfront, Conservia structured the project through its Efficiency as a Service (EaaS) model.
This allows the hotel to renew critical infrastructure without an upfront capital investment, with project costs recovered through an agreed performance-based arrangement.
The approach combines asset renewal, energy efficiency improvements and ongoing performance measurement within a single delivery framework.
The expected result
With construction nearing completion, the project is designed to deliver approximately $650,000 in annual operating savings, including projected reductions of 31% in electricity consumption and 40% in natural gas consumption.
Beyond energy savings, the hotel is expected to benefit from renewed infrastructure, improved system reliability, greater operational visibility and reduced exposure to ageing equipment failures.
The project demonstrates how owners can address major capital replacement requirements while improving building performance, without funding the initial investment themselves.
Energy and financial savings are based on the detailed feasibility study and will be measured and verified following commissioning.
More hospitality results
Similar buildings, measured results.

A large NSW club
NSW

Top Ryde City Shopping Centre
Ryde, NSW

Waverley Council
Waverley, NSW
Optimising Building Performance at Waverley Library